Indicative project timeline
We submitted our DCO application to the Secretary of State on 31 May 2024, it was accepted for examination on 28 June 2024 and development consent was granted on 1 December 2025.
The six-month examination period included a preliminary meeting, multiple issue specific hearings and a total of eight examination deadlines. These sessions covered a wide range of issues and involved helpful discussions between us, the Examining Authority and our stakeholders. The public, statutory consultees and interested parties were given the opportunity to give evidence to the Examining Authority.
The application was granted development consent by the Secretary of State for Energy Security and Net Zero on 1 December 2025.
We anticipate commencing construction in 2027 at the earliest and expect the Morecambe Offshore Windfarm generation assets to be operational by 2030.
Indicative project timeline
2021
-
Non-statutory engagement begins (introductory meetings and website launch)
2022
-
Non-statutory consultation
Ongoing technical and environmental survey and assessment work
2023
-
Statutory consultation
Ongoing technical and environmental survey and assessment work
2024
-
Application submitted for a Development Consent Order (DCO) - May 2024
Application accepted for examination – June 2024
Pre-examination period – June to October 2024
Relevant representation period open – July to August 2024
Examination commenced – October 2024
2025
-
Examination concludes - April 2025
Development consent for Morecambe Offshore Windfarm Generation Assets granted - 1 December 2025
2026
-
Expected Final Investment Decision
2027
-
Earliest anticipated start of construction
2030
-
Expected Commercial Operation Date
Contact us
Should you have any queries, please get in touch with us using one of the methods below:
- Email us: hello@morecambeoffshorewind.com
- Call us: 0800 915 2493 (option 2)
- Write to us: FREEPOST MORECAMBE GENERATION